Figure 2.2.6.3 Responsibility assignment matrix (RAM) showing RACI coding

When the RAM is coded in this way it can also be referred to as a RACI matrix where:

(R)Responsible – conducts the actual work/owns the problem;

(A)Accountable – approves the completed work and is held fully accountable for it;

(C)Consulted – is included in decision making and holds a primary supportive role;

(I)Informed – is kept informed of progress and results.

The RAM provides a clear and concise summary of tasks or deliverables, the specific responsibilities defined within the project procedures, and the level of accountability or contribution expected from named roles or individuals within the project.